Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Column NameDescription
Date

A particular day or period of time, whose format depends on the selected grouping option.

  1. Day: YYYY-MM-DD; for example, 2015-04-13.

  2. Week: YYYY-MM-DD - YYYY-MM-DD; for example, 2015-04-10 - 2015-04-16 (starts from Friday).

  3. Month: YYYY-MM; for example, 2015-04.

  4. Quarter: YYYY-Q[1-4]; for example, 2015-Q2.
HostnameA single hostname of a list of hostnames where license usage took place.
UsernameA single username or a list of usernames.
Usergroup NameThe name of a group of users.
Hostgroup NameThe name of a group of hosts.
Hours UsedThe number sum of hours at least one license when licenses of a particular feature was were used and/or borrowed.
Hours BorrowedThe number sum of hours at least one license when licenses of a particular feature was were borrowed.
Max UsedThe maximum number of licenses used in a particular time period.
Max BorrowedThe maximum number of licenses borrowed in a particular time period.
Max UsageThe maximum allowed level of feature usage, expressed in percentages.

...

Expand
titleExample

To better understand how possible aggregation scenarios work, let’s look at the following example:

ColumnAggregation TypeScenario
Hours Used/BorrowedUser

In our example, the results shown in the report are limited by Day.

 

Scenario 1 

The user uses 1 license for 8 hours.

Calculation: 8 hours = 8 Hours Used

 

Scenario 2

 

The user uses 2 licenses for 1 hour, then 10 licenses for 2 hours and 1 license for 2 hours.

Calculation: 1 2 hour  + 2 20 hours + 2 hours = 5 24 Hours Used

Max Used/BorrowedUser

In this example, the results shown in the report are limited by Day.

 

Scenario 1

The user uses 2 licenses throughout in the same time during the day.

 

Calculation: 2 licenses in the same time = 2 Max Used/Borrowed


Scenario 2
 

The user uses 1 license for an hour in the morning and 1 license for an hour in the afternoon.

Calculation: 1 license in the same time = 1 Max Used/Borrowed


Scenario 3

The user uses 1 license 2 licenses throughout the day . One license is used constantly for the entire day, while the other one is used only for 1 hour.

Calculation: 2 licenses in the same time = 2 Max Used/Borrowed
 

Max UsageUser

In our example, the number of available licenses for a particular feature is 10.

 

Scenario 1

The user uses 2 licenses throughout the day.

 

Calculation: 2 licenses out of 10 licenses = 20%

 

Scenario 2

The user uses 5 licenses throughout constantly for the entire day, but except 1 hour when only 2 licenses are used for 1 hour.
 

Calculation: 5 licenses out of 10 licenses = 50%

 

Scenario 3

The user uses 3 licenses throughout constantly for the entire day, but 8 additionally 5 licenses are used for 1 hour2 hours.

Calculation: 8 licenses out of 10 licenses = 80% 


...